Lowell staff are on the move

Boxes will arrive at Lowell Elementary this month for staff to pack up their spaces in preparation for the move from their school to the temporary West End swing site—formerly Skyline—in August. Lowell staff and students will use the West End swing site for the next two school years, as their new school is built.

Plans for Lowell
Demolition of the existing building is scheduled for February of 2025. Construction of the new school is planned for April 2025 to July 2026. The new Lowell is scheduled to open in fall 2026.

A look ahead:

  • Boxes arrive at Lowell; staff pack up their spaces: June 2024
  • Staff unpack at temporary school building: Aug.2024
  • First day of school: Sept. 9, 2024
  • Construction, spring 2025-summer 2026
  • Move to newly renovated Lowell: Sept. 2026

The design-build team continues to meet with Lowell teachers, staff, parents and community DAC members to gather information and feedback to inform the design of the new school.

Lowell is one of 8 school replacements or historic renovations funded by the construction bond voters passed in 2020.

Translate Our Website

Translate this page by clicking the flag button in the bottom right corner and selecting your preferred language.

Traduzca esta página haciendo clic en el botón de la bandera en la esquina inferior derecha y seleccionando su idioma preferido.

បកប្រែទំព័រនេះដោយចុចប៊ូតុងទង់នៅក្នុងជ្រុងខាងស្តាំខាងក្រោមនិងជ្រើសរើសភាសាដែលអ្នកចូលចិត្តរបស់អ្នក។

Dịch trang này bằng cách nhấp vào nút gắn cờ ở góc dưới cùng bên phải và chọn ngôn ngữ ưa thích của bạn.

오른쪽 하단에 있는 플래그 버튼을 클릭하고 원하는 언어를 선택하여 이 페이지를 번역합니다.

Перекладіть цю сторінку, натиснувши кнопку прапора в нижньому правому куті та вибравши потрібну мову.

Переведите эту страницу, нажав на кнопку с флагом в правом нижнем углу и выбрав желаемый язык.